The project
involved the design and project management of the
installation of a 320 kW, 4.5 tonne chiller plus new
pressurisation, pumping and controls equipment on
the 6th floor roof of a listed building in central
London.
Following receipt of planning permission, the the
lift was carried out on a weekend and involved road
closure and parking bay suspension all organised
through Westminster Council.
|
 |
|